Undisclosed

West London

6No 2MW Generator Sets

2020

Modifications to an existing standby power arrangement for a live data centre facility. This consisted of the replacement of the existing 6No Generator Controllers and the introduction of 2No 8000A Generator Synchronisation Switchboards complete with dedicated new switchrooms without any interruptions to the normal business operation of the facility.